In 1895, the Toronto,
Hamilton and Buffalo Railway company had built a line through Hamilton. Less
than 10 years later, Hamiltonians were getting hostile to the railway because
of the level crossings. Trains stopped at the passenger station on Hunter
street east would block all traffic on busy thoroughfares such as James and
John streets for considerable lengths of time.
In December 1914,
conflict between the T. H. & B. railway and Hamiltonians arose as a result
of repair work being done on a T .H. & B. bridge on Locke street south.
On December 3, 1914,
the Spectator reported that work on the bridge caused prolonged inconvenience :
“The work started
about three weeks ago, and is still far from complete, although it was expected
it would only occupy a week. All street traffic on Locke street over the bridge
is still blocked.
“It was pointed out
this morning by one citizen that the G. T. R. bridge on James street north, was
constructed without the least delay to traffic, ad that one street car track
was always maintained.
“ ‘Why is it that the T. H. & B. cannot
work in a similar manner?’ he asks”1
1 “Object to Delay :
Citizens Complain About Slow Work on Locke Street Bridge”
Hamilton
Spectator. December 3, 1914.
As of December 3,
1914 only one side of the new railway bridge had been completed, while work on
the other side had barely begun. Materials and equipment for the side being
worked on were piled on the completed side, thus continuing full blockage of
traffic.
Citizens, fed up with
the traffic blockage to that point, with the possibility that it could continue
for another three weeks, took their complaints to Hamilton City Hall to little avail
:
“ ‘The T. H. & B.
has an order from the railway board to keep this bridge and roadway in repair,’
said Archie Kappele, secretary of the works department. ‘It is therefore at
liberty to make such repairs whenever it sees fit, and there seems little
chance on the part of the city to compel it to complete the work in any given
time. It might be possible to compel the T. H. & B. to open the completed
side of the bridge for traffic, and if there is evidence of continued delay,
action may be taken along these lines.”1
:
No comments:
Post a Comment